Which chip conveyor is right for long and short metal chips?

As of October 2026

Reading time: 4 minutes

In brief

Chip conveyor selection depends on more than the material and hourly throughput. The actual chip shape, brief peak loads and the entire conveying route are also decisive. A hinged belt conveyor may be a suitable starting point for long chips and tangled chip bundles. Short chips and sludge that settle readily can often be removed using a scraper conveyor. However, general guidance cannot replace an assessment using the actual material to be conveyed.

Why is chip shape so important when conveying metal chips?

A conveyor may appear suitable for a given material based on its data sheet, yet still become blocked during production. The reason often lies in the actual chip shape: short broken chips behave differently from long, tangled chips from turning operations. Selecting conveyor technology solely on the basis of material and hourly throughput can overlook the operating conditions that later cause stoppages.

A sample from the actual process is essential. Simply describing the material as “steel chips” is not enough. How long are the chips? Do they form tangled bundles? Does the material include fine particles or wet chips? Are different materials processed? System design must also account for brief peaks in chip throughput, for example after a tool change, and for the points where material is transferred or lifted. A photograph helps, but a representative material sample and information about the production cycle are even more useful.

Chip shape can also change within the same production process. A different tool, modified cutting parameters or a new material can alter the material being conveyed. The sample should therefore represent both normal operation and the most demanding known conditions. An average value in kilograms per hour alone says little about whether a tangled bundle of chips could block the inlet.

Hinged belt conveyor or scraper conveyor for metal chips?

A hinged belt conveyor may be a suitable starting point for long chips and tangled chip bundles. Short chips and sludge that settle readily can often be removed along a trough using a scraper conveyor. The chip conveyor overview also groups conveyor types by chip characteristics. However, manufacturer examples show that belt construction and discharge details are particularly important for sticky or heavily tangled chips. General guidance cannot replace testing with the actual material to be conveyed.

 

Hinged belt conveyor

Scraper conveyor

Typical conveyed material

Long chips and tangled chip bundles; depending on the design, short chips as well

Short chips and sludge that settle readily

Conveying principle

Material is carried on interconnected hinged plates

Flights push the material along a trough

What to check before selection

Infeed, chip entanglement, belt construction and discharge

Chip shape, settling behaviour and discharge

The table provides initial guidance. The appropriate design also depends on chip throughput, the metalworking fluid used and the conveying route.

Where can blockages occur during chip removal?

Three areas deserve particular attention during planning:

→

At the inlet: Tangled chip bundles arrive in bursts at an infeed area that is too small.

→

At bends and inclines: Long chips become entangled, or material falls back.

→

At the discharge point: The conveyor handles the throughput, but a hopper or container obstructs the discharge.

These points provide a planning checklist rather than a universal diagnosis of faults. The metalworking fluid is equally important. It should drain off at suitable points rather than leave the system uncontrolled with the chips. Depending on the process, subsequent chip separation, removal of residual fluid or transfer to a chip storage bunker may be appropriate.

A simple thought experiment helps during preliminary assessment: What happens if two machines discharge chips at the same time while material is already present at the collection point? This often highlights requirements for buffering, conveying speed and control. The entire route to the container must be assessed under the most demanding conditions, rather than considering only the conveyor section immediately in view.

What information is needed to specify a chip conveyor?

Useful information includes the workpiece material, a representative chip sample, chip shape, average throughput and peak loads, the type of metalworking fluid and the liquid content of the chips, and the number of machines.

Sketches should show the inlet, conveying route, height difference and discharge point. This information helps determine whether a single conveyor is sufficient or an interlinked conveyor system is required. The appropriate conveyor must be able to handle the most demanding actual operating conditions.

Frequently asked questions

Which chip conveyor is suitable for long metal chips?

A hinged belt conveyor may be a suitable starting point for long metal chips and tangled chip bundles. The actual chip shape, belt construction, inlet and discharge point remain decisive. Suitability should be checked using a representative chip sample.

Short chips and sludge that settle readily can often be removed along a trough using a scraper conveyor. Selection also depends on chip throughput, the metalworking fluid and the conveying route.

Brief peak loads can overload the inlet or a transfer point even when the average hourly throughput is within the conveyor’s capacity. Intermittent chip discharge and simultaneous discharge from several machines must therefore also be considered.

The workpiece material, a representative chip sample, chip shape, average throughput and peak loads, the type of metalworking fluid and the liquid content of the chips, and the number of machines. A sketch should show the inlet, conveying route, height difference and discharge point.

Suitable solutions from KÖBO ECO>PROCESS